# XZBT 0.1 Verification Gates **Status:** Planning checklist; every check is pending **Related resources:** [PRD](../XZBT_0-1_MVP_Product_Requirements_Document.md), [decisions](XZBT_0-1_Gap_Closure_Decisions.md), [format specification](XZBT_0-1_Format_Specification.md) No tests, browser prototypes, benchmark results, or soak results have been run as part of the gap-closure documentation. Mark a check complete only with linked evidence. A recorded design decision is not a passing test. ## Phase 0 and later gates Drafting the implementation plan may proceed now. Before committing the deployment architecture, pass GC1. Before implementing shared runtime semantics, complete the shared portions of GC2 and GC3-GC5 contracts and their expected traces. Early GC6 measurements inform expensive subsystem design. Full conformance and real-duration soak results remain release requirements. Subsystem-specific format details can be completed in dependency order as planned tasks. Do not require the finished engine or eight-hour soak before creating the plan. | Gap | Decision | Evidence status | Gate placement | | --- | --- | --- | --- | | GC1 | Recorded | Not run | Phase 0, before deployment architecture commitment | | GC2 | Recorded; format draft partial | Contracts and fixtures incomplete | Shared contracts in Phase 0; subsystem contracts before their implementation | | GC3 | Recorded; transition details open | Traces and tests pending | Shared resolver contract before Phase 2; tests with implementation | | GC4 | Recorded; audio mapping details open | Prototype and tests pending | Clock contract in Phase 0; synchronization tests in audio integration | | GC5 | Recorded; hook/queue details open | Traces and tests pending | Ownership contract before actions/audio; full tests with scenarios | | GC6 | Recorded; thresholds provisional | Reference setup and benchmark absent | Early combined-load prototype; development and release acceptance | | GC7 | Recorded | Plan/build/library checks pending | Milestone planning, then library/build integration | ## 1. GC1: Direct-file feasibility - [ ] Record OS, browser version/profile, launch path, and storage mode. - [ ] Open the artifact directly from disk with network unavailable. - [ ] Import two exhibits with the ordinary file picker and activate each. - [ ] Save exhibit definitions, per-exhibit parameters, selection, and master volume to IndexedDB. - [ ] Close the browser fully, reopen the same HTML, and restore the cached library and settings without selecting source files again. - [ ] Verify user-initiated audio unlock and resumed playback. - [ ] If needed by the audio design, load engine-owned AudioWorklet code from the single-file artifact. Otherwise document why this check is not applicable. - [ ] Test renamed and moved HTML files; record observed storage behavior and the support boundary. - [ ] Test unavailable/failed storage; session playback works and the UI explains lack of persistence. - [ ] Test directory import/remembered handles where available and ordinary-picker fallback where unavailable or permission is denied. **Evidence:** prototype artifact, reproducible steps, environment record, observed results. If ordinary-mode persistence fails, reopen decision 1 before dependent architecture commitment. ## 2. GC2: Format contract completeness - [ ] Complete shared document, type, reference, ValueSpec, ConditionSpec, time, and ownership contracts. - [ ] Fill the format-specification contract register in subsystem dependency order. - [ ] Implement an internal structural schema plus separate semantic validation. - [ ] Provide complete valid and invalid fixtures with expected diagnostics. - [ ] Reject unsupported versions, unknown behavior fields, invalid reference types, recursive components, illegal graph cycles, and excessive resources. - [ ] Produce two contrasting complete audiovisual exhibits early; expand toward all PRD challenge cases. - [ ] Reconcile prior conversation proposals into the local documents; resolve conflicts explicitly. **Evidence:** versioned specification/schema/fixtures and validation results. Naming a node or behavior does not close its contract. ## 3. GC3: Resolution semantics - [ ] Record exact target capabilities, override defaults, smoothing, and interrupted transition rules. - [ ] Define expected traces for a bound bus gain receiving a direct override. - [ ] Define expected traces for a parameter override feeding a binding. - [ ] Verify stored user edits during masking and release toward the updated lower value. - [ ] Verify priority ties and competing duration/scenario overrides. - [ ] Verify automation continues while masked and permitted modulation applies after an override. - [ ] Verify numeric clamps and unsupported target/stage diagnostics. - [ ] Reject conflicting bindings and dependency cycles without introducing undocumented delays. **Evidence:** contract examples and deterministic resolver tests when implemented. ## 4. GC4: Time and reproducibility - [ ] Define logical tick ordering, maximum work per turn, long-stall behavior, audio lookahead, and audio unlock alignment. - [ ] Define PRNG algorithm, seed normalization, and stream derivation for the runtime version. - [ ] Compare simulation traces at different render frequencies using the same logical inputs. - [ ] Hide/restore the document and explicitly pause/resume; no missed wall-clock work is replayed. - [ ] Verify visibility restoration does not undo an explicit pause. - [ ] Verify audio suspends/resumes consistently and expired pre-unlock one-shots are not replayed. - [ ] Verify manual SAMPLE does not perturb cadence/scenario random streams. - [ ] Use deterministic signal fixtures for audio-reactive decision tests. - [ ] Distinguish accelerated logical tests from real-time audio behavior and soak tests. **Evidence:** clock/PRNG contract, logical traces, and browser/audio observations. No cross-device pixel or waveform equality claim is required. ## 5. GC5: Ownership and failure - [ ] Define hook ordering, allowed hook actions, failure propagation, cleanup deadlines, deferred expiry/order, and dispatch-budget behavior. - [ ] Start resources through nested events and confirm inherited scenario ownership. - [ ] Verify duration overrides terminate with their owner and bounded releases eventually dispose. - [ ] Verify persistent state mutations survive a later critical failure. - [ ] Inject failures into startup, ordinary actions, and termination hooks; cleanup still completes. - [ ] Verify condition triggers require a false condition before rearming. - [ ] Verify at most one pending deferred request per definition, expiry, and eligibility recheck. - [ ] Exercise event/scenario feedback and show bounded dispatch with diagnostics. - [ ] Repeat completion/cancellation/failure cycles; counters return to baseline after releases finish. **Evidence:** lifecycle traces, resource-count samples, and failure-injection results. ## 6. GC6: Performance and audio acceptance - [ ] Record CPU/GPU/RAM, OS, browser version, 1920 x 1080 viewport, device-pixel ratio, sample rate, and relevant power settings. - [ ] Fix benchmark exhibit/version/seed and counts for particles, links, trails, effect passes, audio nodes, and concurrent voices. - [ ] Prototype combined visual/audio load early and record supported limits. - [ ] Define warm-up duration, measurement window, frame interval sampling, and retained-memory sampling method before collecting acceptance data. - [ ] Check the provisional p95 frame interval threshold of less than 33.3 ms and report progress toward the 60 FPS target. - [ ] Record active resource baselines and verify expected return after repeated lifecycle operations. - [ ] Specify and test digital output peak ceiling, numerical tolerance, finite samples, release behavior, and unavoidable master routing. - [ ] Stress overlapping recipes and listen for clicks, clipping, and objectionable release artifacts. - [ ] Run a two-hour development soak and an eight-hour release soak; record retained-memory trends, resource counts, frame intervals, audio glitches, and scheduler growth. **Evidence:** fixed workload, environment, measurement method, results, and investigated anomalies. Any threshold revision must be recorded before rerunning acceptance; do not silently change the benchmark to produce a pass. ## 7. GC7: Scope, updates, and build - [ ] Map all PRD completion criteria and challenge cases to milestones and evidence. - [ ] Integrate two contrasting exhibits early; make Phase 9 the completion/audit phase for all five reference exhibits. - [ ] Define import equality and parameter compatibility precisely. - [ ] Verify identical imports are no-ops and changed same-ID content requires an explicit replacement choice. - [ ] Verify invalid refreshes leave the last valid definition and configuration intact. - [ ] Verify compatible parameter preservation, numeric bound changes with notice, removed/new parameters, and incompatible-type/enum resets. - [ ] Validate and prepare a candidate without observable playback before stopping the working exhibit. - [ ] Inject activation failure; dispose of the candidate and attempt a fresh restart of the previous exhibit with saved settings. - [ ] Build separate source modules into one self-contained HTML artifact reproducibly. - [ ] Test the delivered artifact directly and offline; no external runtime scripts, modules, assets, fonts, or CDN requests are required. **Evidence:** implementation-plan coverage, library failure tests, build instructions, and artifact verification. ## Evidence record template For each result, record gate/check ID, date, specification revision, implementation revision or artifact hash, environment, fixture/seed, procedure, expected result, actual result, pass/fail/not-applicable status, linked logs or measurements, and unresolved limitations. A not-applicable result requires a reason. Do not prefill results from intended behavior.