Document MVP planning milestones

This commit is contained in:
2026-08-17 01:09:07 -07:00
parent f3688cd62b
commit 21b845d16e
2 changed files with 104 additions and 0 deletions
@@ -0,0 +1,51 @@
_model: devlog-entry
---
schema_version: 1
---
title: Twungeon adopts an acceptance-led MVP build plan
---
date: 2026-08-17
---
author: ChatGPT 5.6 Sol High Reasoning and Christopher Chambers
---
summary: With the technical specification approved, Twungeon gained a sequenced ten-phase build checklist and 33 traceable acceptance tests that define the evidence required before the MVP can be called complete.
---
tags: pre-development, technical specification, acceptance testing, build checklist, MVP, planning, Twitch, testing, documentation
---
source_commit: f3688cd62bccc25c22a9780f65d719104989104f
---
body:
Twungeon's technical specification was approved as the implementation baseline,
and planning moved into an acceptance-led build sequence. This remains a design
and execution milestone: no runtime feature, Twitch integration, or viewer test
is represented as complete merely because its checklist now exists.
The build plan organizes implementation into ten gated phases after the planning
baseline. It begins with reproducible tooling and a framework-independent domain
core, then adds dungeon generation, the local turn loop, Goblin behavior, player
and floor lifecycles, production-shaped APIs and views, Twitch identity and chat,
Bits resurrection, and finally independent setup and real-viewer validation.
Each phase has a checkpoint intended to catch failures before work moves into a
more expensive external integration layer.
The acceptance matrix assigns AT-001 through AT-033 directly to the PRD's 33
success criteria. It distinguishes automated domain evidence from browser,
clean-install, live Twitch, multi-viewer, documentation, usability, and concept-
validation evidence. A mock cannot close a live Twitch criterion, and a checked
item can be reopened if later evidence invalidates it.
The plan also defines standard quality gates, evidence records, clean-checkout
verification, change control, and the final MVP acceptance decision. Planning
work is checked off where it is complete; every implementation and validation
item starts unchecked.
The execution baseline is the
[Twungeon MVP Acceptance-Test and Build Checklist](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_Acceptance_Test_and_Build_Checklist.md),
used with the approved
[technical specification](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_Technical_Specification.md)
and the authoritative
[MVP PRD](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_PRD_Current.md).
The repository baseline for this planning milestone is
[commit `f3688cd62bccc25c22a9780f65d719104989104f`](https://git.labyricorn.com/Labyricorn/Twungeon/commit/f3688cd62bccc25c22a9780f65d719104989104f).