_model: devlog-entry
|
||||
---
|
||||
schema_version: 1
|
||||
---
|
||||
title: Twungeon adopts an acceptance-led MVP build plan
|
||||
---
|
||||
date: 2026-08-17
|
||||
---
|
||||
author: ChatGPT 5.6 Sol High Reasoning and Christopher Chambers
|
||||
---
|
||||
summary: With the technical specification approved, Twungeon gained a sequenced ten-phase build checklist and 33 traceable acceptance tests that define the evidence required before the MVP can be called complete.
|
||||
---
|
||||
tags: pre-development, technical specification, acceptance testing, build checklist, MVP, planning, Twitch, testing, documentation
|
||||
---
|
||||
source_commit: f3688cd62bccc25c22a9780f65d719104989104f
|
||||
---
|
||||
body:
|
||||
|
||||
Twungeon's technical specification was approved as the implementation baseline,
|
||||
and planning moved into an acceptance-led build sequence. This remains a design
|
||||
and execution milestone: no runtime feature, Twitch integration, or viewer test
|
||||
is represented as complete merely because its checklist now exists.
|
||||
|
||||
The build plan organizes implementation into ten gated phases after the planning
|
||||
baseline. It begins with reproducible tooling and a framework-independent domain
|
||||
core, then adds dungeon generation, the local turn loop, Goblin behavior, player
|
||||
and floor lifecycles, production-shaped APIs and views, Twitch identity and chat,
|
||||
Bits resurrection, and finally independent setup and real-viewer validation.
|
||||
Each phase has a checkpoint intended to catch failures before work moves into a
|
||||
more expensive external integration layer.
|
||||
|
||||
The acceptance matrix assigns AT-001 through AT-033 directly to the PRD's 33
|
||||
success criteria. It distinguishes automated domain evidence from browser,
|
||||
clean-install, live Twitch, multi-viewer, documentation, usability, and concept-
|
||||
validation evidence. A mock cannot close a live Twitch criterion, and a checked
|
||||
item can be reopened if later evidence invalidates it.
|
||||
|
||||
The plan also defines standard quality gates, evidence records, clean-checkout
|
||||
verification, change control, and the final MVP acceptance decision. Planning
|
||||
work is checked off where it is complete; every implementation and validation
|
||||
item starts unchecked.
|
||||
|
||||
The execution baseline is the
|
||||
[Twungeon MVP Acceptance-Test and Build Checklist](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_Acceptance_Test_and_Build_Checklist.md),
|
||||
used with the approved
|
||||
[technical specification](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_Technical_Specification.md)
|
||||
and the authoritative
|
||||
[MVP PRD](https://git.labyricorn.com/Labyricorn/Twungeon/blob/main/Twungeon_MVP_PRD_Current.md).
|
||||
|
||||
The repository baseline for this planning milestone is
|
||||
[commit `f3688cd62bccc25c22a9780f65d719104989104f`](https://git.labyricorn.com/Labyricorn/Twungeon/commit/f3688cd62bccc25c22a9780f65d719104989104f).
|
||||